  • 21 June 2015

    Go fund me page for the Leicester iGEM team was first created as such: Leicester iGEM Go fund me

  • 22nd June 2015

    09:00-18:00

    Start of Labs

    Making of agar plates with chloramphenicol, ready to used the next day to streak bacteria

  • 23rd June 2015

    09:00-18:00

    Start of Measurement Study

    -Suspension of parts required for each device required in the measurement study. The parts (Promoter and GFP) were then transformed into DH5(alpha) bacteria. This is then placed on agar plates made the day before.

  • 24th June 2015

    09:00-18:00

    Measurement Study

    Bacteria produced from the streaks from the previous day are then restreaked again

  • 25 June 2015

    09:00-18:00

    Measurement Study

    The restreaks are taken and placed into liquid culture

Week 2

Week 1

  • 21 June 2015

    Go fund me page for the Leicester iGEM team was first created as such: Leicester iGEM Go fund me

  • 22nd June 2015

    09:00-18:00

    Start of Labs

    Making of agar plates with chloramphenicol, ready to used the next day to streak bacteria

  • 23rd June 2015

    09:00-18:00

    Start of Measurement Study

    -Suspension of parts required for each device required in the measurement study. The parts (Promoter and GFP) were then transformed into DH5(alpha) bacteria. This is then placed on agar plates made the day before.

  • 24th June 2015

    09:00-18:00

    Measurement Study

    Bacteria produced from the streaks from the previous day are then restreaked again

  • 25 June 2015

    09:00-18:00

    Measurement Study

    The restreaks are taken and placed into liquid culture