Team:Cork Ireland/Notebook

Notebook

Loading menubar.....

Wetlab Progress

Week 1: 25-May-2015

After many hours of pooling ideas together the team decided on the project idea of optimising and further developing a molecular diagnostic tool in March. Team members entered the lab in late May to begin training in molecular biology and microbiological laboratory techniques such as PCR, bacterial transformations, gel electrophoresis and so on.

Week 2: 1-June-2015

The team entered the lab and spent a great deal of time investigating the best way to approach the project to ensure maximum productivity with a limited amount of time. Cost of the project was also greatly considered. The following parts from the distribution kit were transformed into DH5α cells.

  • BBa_K592026
  • BBa_K592100
  • BBa_K952003
  • BBa_J06702
  • BBa_K1357009
  • BBa_K395602

The team ran into trouble on the first large transformation, so it was repeated over the course of the week. Liquid culture of the following parts were prepared:

  • BBa_K1357008
  • BBa_J23119
  • BBa_K59602
  • BBa_K592100
  • BBa_K592026

Plasmid preps of the above parts was also performed. A restriction digest using XbaI and PstI was performed to see if the plasmid backbone and the respective parts were present. During the course of the week the first biobrick assembly of parts BBa_J23119 (Promotor) & BBa_K1357008 (Purple fluorescent protein) was attempted after a restriction digest had been performed. The different assembly steps were repeated over the week in order to try achieve a successful assembly.

Week 3: 8-June-2015

This week was spent experimenting with different ligations such as; BBa_J23119 (Promotor) as the backbone & part BBa_K1357008 (Purple fluorescent protein) as the insert. These ligations were performed to work on the colour readout of the system. The various ligations were transformed into competent cells to see if the ligations were successful, if successful the CFUs would glow the colour as determined by the biobrick part. Primers for the detector plasmid construction were designed by the team members and ordered from IDT. This allowed the detector to be constructed using an additional PCR step.

The ligated plasmids were extracted from the transformed cells, digested and ran on a gel to see if the ligation was successful. This was done in an attempt to understand the logistics of the ligations and the E.coli cells. The products of detector construction were ran on agarose gels at various stages in construction to determine if the construction was successful at every stage.

Also this week the sensitivity of the Digested-HPV55 detector was tested. Detectors constructed by PCR and a quadruple digest were tested to see if different detector construction could influence the sensitivity of the system. The PCR detectors were tested after a minimum of a Dpn1 digest, PCR clean-up & quadruple digest. Further steps in the detector construction included a decoy reaction to remove all template DNA and another PCR clean-up.

image

Week 4: 15-June-2015

Further ligations of colour producing biobrick parts were performed to optimise the colour readout of the system. 3A assembly with Kanamycin and Chloramphenicol was performed as an alternative to digestion, gel extraction and ligation.

The transformation efficiency of the DH5α cells was tested this week using the iGEM Transformation efficiency kit.

This week marked the beginning of the testing of the specificity of the HPV-55 detector plasmid. Both the Digested-HPV55 and the PCR-HPV55 were tested. This was done by setting up a detector reaction using a series of mutated oligos that were designed by the team and synthesised by IDT.

image

The GFP plasmid was tested to see if any background was present, this allowed the results from the specificity testing to be analysed with a higher degree of confidence.

image

After each detector construction, the functionality of the detectors were tested by gel electrophoresis (to check for detector presence at right MW) and transformations were carried out using both positive and negative controls.

Week 5: 22-June-2015

The team signed up to participate in the Interlab study.

A HPV-30 base pair detector was constructed and a series of mutated oligos were designed and synthesised in order to test the specificity of this detector.

image

It was investigated to see if increased or decreased target length would affect the specificity of the detector using oligos illustrated in figure below.

image

HPV-55 detector was reacted with the 30bp top strand target, HPV-30 was reacted with the 55bp top strand target.

image image

For the colour readout of the system, the RFP from the transformation efficiency kit was purified from transformed cells and implemented into the detector reaction protocol as a transformation efficiency control. RFP in dilutions of 1:100, 1:200, 1:1000 were tested.

image

The interlab study was started this week, the different parts needed were taken from the distribution kit and transformed. After successful transformations of the three promoters and the GFP generating device, plasmid preps were done on the devices in order to prepare them for cloning.

Week 6: 29-June-2015

The HPV-30bp detector was tested with the series of mutated oligos in order to see if it was more specific that the HPV-55 detector.

image

While investigating the specificity of the system, the different temperatures of the detector reaction were investigated and calculated in order to minimise hybridisation (see WHATEVER SECTION WILL HAVE THOSE PROTOCOLS OR PUT IN LINK). This was investigated using the HPV-55bp detector. This week the work into developing differently timed detector reactions with different temperatures to minimise non-specific binding of DNA to the target site were tested in the plasmid. This was investigated thoroughly over the course of the next few weeks.

image

A great variation in transformation efficiency was noted between different aliquots of cells. This lead to the development of a new transformation protocol. For the construction of the devices for the interlab study, two methods of assembly were trialed due to difficulties in cloning, the methods were 3A assembly and the traditional restriction digest/ligation method. Two of the devices i.e Device 1 and 2 were constructed in the initial stages but Device 3 proved to be more difficult to clone successfully.

Week 7: 6-July-2015

Experimentation into the various detector reaction temperatures continued. The IDT Oligo Analyser was used to calculate the melting temperature based on [Mg+2] of 0.1 and [Na] of 0. A diluted amount of target was also tested, 1 microlitres of a 1 in 10 dilution instead of 1μl of an undiluted target.

Overnight liquid cultures were prepared for the constructed devices 1 and 2, the overnights were made in triplicate i.e three biological replicates were made. Colony PCR was done on the non-green fluorescent colonies present on the plates where the ligated device 3 was transformed, this was done using the VF2 and VR2 primers, the colony PCR done revealed that the correct size device was present in some of the colonies that were screened. Later this week, following more ligations, colonies that showed green fluorescence were evident on the plates, these colonies were taken grown up overnight in a liquid culture and re-transformed to reveal more green-fluorescent colonies from which the three biological replicates were taken.

Week 8: 13-July-2015

Over the last few weeks, a significant variation in transformation efficiency was observed. For this reason, detector reactions on the RFP without the detector plasmid was performed to investigate if the different temperatures had an effect on the RFP.

Inconclusive results were drawn from the different temperatures in the detector reaction so investigation was ceased.

image

The team commenced in developing a new transformation protocol. This was investigated this week.

As an alternative to a quadruple digest, detector construction was attempted on an agarose gel. This idea was inspired by reading many papers on the subject. Plasmid preps were made of all overnights that were successful and these were subsequently diluted 1:1000 and re-transformed whereby a greater proportion of the colonies showed green fluorescence. 3 biological replicates were taken from these and by the 14th July, fluorescence was ready to be measures using the plate reader. As controls, colonies without promoters but containing the GFP generator I13504 were grown overnight and a LB media inoculated with antibiotic was left overnight at 37°C with the rest of the samples.

Each of the biological replicates were tested three different times using the plate reader. The average and standard deviation of both technical replicates and biological replicates was obtained. This average was then divided by the OD at 600nm.

Digests were performed on all the devices to show that they were the correct size by restriction mapping. These liquid cultures were diluted and re-transformed again to give biological replicates whose fluorescence data was closer in value.

Week 9: 20-July-2015

The specificity of the HPV-30bp detector was further investigated. The different detector reaction temperatures were still being experimented on using the HPV-55bp detector. Plasmid mini-preps were performed on non-specific colonies. These were mismatched oligos that gave a positive result in the testing process. The plasmid mini-preps were performed in order to prepare the samples for sequencing. This was done in an effort to understand what was happening with the detector plasmid and mismatched oligo to indicate a positive result. The team hoped that the results would reveal what the repair mechanisms of the E.coli cells were doing to the detector plasmid.

Detector reactions were carried out with phosphorylated and nonphosphorylated oligos and detector plasmids to understand whether or not any difference would be evident in the number of CFUs, this was carried out as a method to detect if E.coli would naturally phosphorylate the oligos when they’re transformed into E.coli.

Week 10: 27-July-2015

This week the HPV-55bp and the HPV-30bp detectors were reacted with male mouse genomic DNA samples to assess the background of the detectors.

When the results of the specificity testing for the detectors were analysed, a smaller target yielded higher specificity. For this reason, a HPV-24bp detector was constructed using PCR.

Week 11: 3-August-2015

A selection of detectors were constructed and their functionality was investigated by gel electrophoresis and detector reactions.

image

The week was spent perfecting the different detectors. Both male and female mouse genomic DNA was digested using a variety of enzymes and it was then ran on a gel to see if the digest was successful, however complications arose as DNA was not seen on gel.

image

This digested DNA was used to investigate the background levels from the new detectors, thus investigating their specificity.

Week 12: 10-August-2015

More male and female mouse genomic DNA was digested using different enzymes to investigate the background levels from the new detectors.

Week 13: 17-August-2015

More genomic DNA need to be extracted from mice liver, this genomic DNA was verified to be there by using a nanodrop and running it on a gel. Both male and female samples were digested with PstI. Detector reactions were then done using the HPV 24 base pair detector and the digested genomic DNA samples to detect for background due to unspecific hybridisation. This was performed twice in triplicate using normal and high transformation efficiency cells. Four more HPV 30 base pair detectors were also partly constructed this week. The sequences needed for the mycobacterium detector were identified and study was done to construct this.

Week 14: 24-August-2015

Detector reactions were carried out on the SRY 32 base pair detector using PstI digested genomic DNA, this would show whether the detector could be used in a real world application. The data was finalised and entered for the interlab study. 4 more HPV 30 base pair detectors were completed early this week. The oligos and primers for the mycobacterium detector were ordered this week.

Week 15: 31-August-2015

The mycobacterium detector was constructed this week, this involved amplifying it by PCR, digesting the PCR product with DPNI, doing a PCR clean-up, digesting the constructed detector with BamHI, KPNI, NtBspQ1,NbBtsI, reacting the product with decoys and doing a PCR clean-up. The detector was then tested by doing detector reactions.

The SRY detector was again tested with genomic male and female DNA using highly competent cells. Complications again arose as transformation efficiency was poor and controls did not work.

image

Week 16: 7-September-2015

Construction of the SRY 32 bp detector was started this week. The initial PCR amplification didn’t work and so the PCR amplification steps were changed to accommodate this. The mycobacterium detector with GFP was transformed.

Week 17: 14-September-2015

Work was done to test the SRY 32bp detector and the Mycobacterium detector constructed. Biobricks were assembled and prepared for submission to the Registry All results were gathered and finalised for presentation on the wiki.

Preparation for Giant Jamboree!